Job Actual Costs Summary
Reports
While the Job Actual Costs Report prints a row for each amount type, the Job Actual Costs Summary prints a row for each job and each amount type will print in a separate column.

Job Actual Cost Summary
Watch a video
What's new in 2018.05? (New variables: Indirect Overhead, Labor Benefits Overhead) (35s)
Updated 15May2018
Printing Job Actual Costs Summary
1. Open Connect Project Accounting > Reports > Job Actual Costs Summary.
2. Enter the Report Dates.
All of the transactions with a transaction date in the date range will be included in the report.
How do I set up the Selection Criteria?
How do I set up the Report Order?
3. Set up the Include options.
An open job allows users to add transactions and modify or delete existing transactions that relate to the job. On the other hand, users cannot add, modify, or delete transactions from a closed job. Use Open Jobs to include transactions on jobs assigned to an active or closed - preliminary job status. Use Closed Jobs to include transactions on jobs assigned to a closed - final job status.
What do you want to do?
I want to print actual costs on open jobs. Click to select the checkbox titled Open Jobs.
I want to print actual costs on closed jobs. Click to select the checkbox titled Closed Jobs.
4. Click Print (CTRL+P).
The report prints.
Updated 12Dec2017