Remove estimates that are not connected to a permit.
An estimate is a tentative judgment of the approximate value. When you use Community Development to estimate a permit, the application saves the estimate and all of the information that you used to create the estimate in a file. You can clean up the database by deleting estimates that are not connected to a permit.
Before you get started
-
Back up the database, see the help topic titled How do I back up the database?
Deleting estimates
1. Open Connect Community Development > Organization > Delete Estimates.
2. Enter the Delete Estimates Prior To.
This date calculates based on the setting in the Organization table. However, you can enter a different date. To change way the date calculates, edit the number stored in the Keep x Months of Estimates field in Organization > Organization.
Is the Delete Estimates Prior To correct?
-
Yes, the date is correct. Continue to the next step.
-
No, the date is NOT correct. Click on the Delete Estimates Prior To field and enter a different date. Remember, the routine will delete all of the estimates with a transaction date that occurs on or before the Delete Estimates Prior To field.
3. Click GO (CTRL+G).
The estimates are deleted.